The standard consideration period for a residential project is eight weeks. This is the official time frame for your local council to carry out a consultation with the neighbours and reach a decision. We recommend allowing a minimum of ten weeks from submission to decision as, in practice, the process always takes slightly longer for the following reasons:
  • The decision period clock only starts ticking once the application is validated by the Council, This requires then to check that the forms are completed correctly and that the submission contains all the necessary drawings, statements and reports.
Validation can take anything from a few days to couple of weeks when the council is very busy, which is most of the time…
  • Although required by law to provide a decision within the statutory eight weeks period, it is not uncommon for councils to miss the deadline of the consideration period, normally only by a few days, sometimes longer.
While there are some effective measures to apply pressure, which we do not hesitate to use when appropriate, it is generally beneficial for the project to bear with the council a little longer.
  • In some cases the council may ask us as your agent for an extension of time, this may be requested due to internal reasons or as an acceptable result of a professional discussion that we are conducting with them about certain aspects of the application that they are not sure about.